West review (RJ, MH, MP circles) | Sync plan F3 vs current outlook
Project input sheet · edit the outlook (Tab / Enter to move on); grey line under each milestone cell = F3 sync plan and the difference · edited cells are yellow
Month, quarter, half and FY
All projects × milestones
Consolidated: FY27 sync plan F3 vs current outlook
Unit
Outlook FY27 = Apr–Sep actuals + October (actuals to date + forecast for the rest of the month) + Nov–Mar from the input sheet. F3 FY27 = sync plan Apr–Mar for the same rows (see the project mapping under the input sheet). Opening stock is not included in either. Bars show only projects that move; hover a bar for its numbers.
Leekasar RfC −20 is a booking difference, not a slip: the RJ file carries 20 RfC in opening stock that the sync plan has in Apr-26 (every later month is also one month earlier in the RJ file). Including opening stock both reach 93.
Yanara: RfC starts in Dec instead of Nov (−15); CoD of 20 in Mar-27 is not in F3. Shiv LTA +1: 47 in the outlook vs 46 in the sync plan.
MH / MP: outlook follows the Excel sheet as submitted; see the QC notes for data gaps (e.g. Mahindra Susten 3.3 MW largely missing from the sync plan).
Only projects in the Excel sheets are covered; other West rows in the sync plan (e.g. Leekasar Juniper4B, row 151) have no outlook yet.